Home Renovation Order of Works: A 10-Step Singapore Plan

A renovation programme works when every trade receives a ready workfront, the previous work has been checked, and approvals and long-lead decisions are not left to the start date.

Published 15 July 2026 · Reviewed 15 July 2026 · By All-in-One Fix & Move · Reviewed by All-in-One Fix & Move

Quick answer: A practical home-renovation order is: confirm scope and approvals, freeze the layout, complete protection and demolition, run concealed services, close walls and ceilings, waterproof and tile wet areas, install floors, complete carpentry, fit fixtures, then test and hand over. Dependencies matter more than the calendar; site conditions and approval lead times can change every programme.

The 10-step order of works

  1. Freeze the brief, layout and approval route. Confirm room uses, demolition, wet-area changes, electrical load and points, plumbing, air-conditioning routes, finishes and appliances. Identify HDB, MCST, landlord or other approvals before booking work.
  2. Validate the site and mobilise. Recheck dimensions, services and existing defects; photograph condition; confirm access, working-hour and protection rules; approve samples; order long-lead items; and issue the coordinated drawings.
  3. Protect, isolate and demolish carefully. Protect retained finishes and common areas, arrange safe service isolation by the appropriate trade, then carry out only approved hacking, dismantling and disposal.
  4. Form the new shell. Complete agreed masonry, kerbs, partitions, plaster bases and opening adjustments so later service and finish dimensions have stable reference points.
  5. Install first-fix concealed services. Coordinate electrical wiring and boxes, plumbing and drainage, air-conditioning pipes and drains, data routes and any ventilation provisions before surfaces close. Photograph routes and test as specified.
  6. Close surfaces and waterproof wet areas. Close approved walls and ceilings after inspection, prepare substrates, apply the specified waterproofing system and complete the agreed water or flood test before covering it.
  7. Complete tiles, floor bases and finish preparation. Set falls to drains, install tiles and grout, level approved dry-area bases, complete ceiling details and prepare walls. Protect completed work from following trades.
  8. Sequence final floors, painting and carpentry. The exact order depends on the floor and joinery details. Confirm final carpentry dimensions from agreed finished surfaces or datums, then protect floors and finished paint while units are installed and adjusted.
  9. Install second-fix items and commission. Fit switches, lights, sanitary fixtures, taps, doors, hardware, appliances and air-conditioning equipment in the coordinated order. Licensed trades should inspect, test or certify work where required.
  10. Test, rectify, clean and hand over. Check water flow and drainage, leaks, electrical operation, doors and drawers, sealant, finishes and equipment; record defects; retest rectified items; collect warranties, manuals and approvals; then complete final cleaning and handover.

Critical dependencies that prevent rework

Before this workConfirm this dependencyWhy it matters
Hacking or structural-looking changesApproved drawings, permit status and site markingAvoids unauthorised work and accidental damage to retained construction or services
Closing walls or ceilingsConcealed routes complete, inspected, photographed and tested as specifiedReduces destructive reopening for missed wiring, pipes or drainage
Covering wet-area waterproofingSubstrate, upturns, penetrations and agreed test acceptedDefects are easier to correct before tiles and fixtures conceal the system
Releasing custom carpentryFinal dimensions or a documented finished datum, plus appliance specificationsPrevents clashes, wrong gaps and unusable service access
Installing sanitary fixturesTiles, falls, outlets, waterproofing and support points readyProtects the wet-area system and helps fixtures align with actual finishes
Final handoverTesting records, defect close-out, manuals, warranties and spare materialsTurns visual completion into an auditable, usable handover

Illustrative 8-week programme

This is an example for a controlled, smaller whole-home scope after design, required approvals, access arrangements and key material decisions are ready. It is not a quotation, promise or universal duration.

WeekIllustrative focusRelease gate
1Protection, safe isolation, approved demolition and strip-outExisting conditions and demolition extent confirmed
2Masonry, partitions and first service routesCoordinated layout and point schedule frozen
3First-fix electrical, plumbing, aircon and ceiling frameworkRoutes inspected and documented before closure
4Wet-area substrate, waterproofing and agreed test; wall closureTest accepted before covering
5Tiling, floor-base work, ceiling closure and paint preparationWet-area falls and finish set-out checked
6Painting stages, selected final flooring and carpentry deliverySite dimensions and fabrication already confirmed
7Carpentry adjustment, doors, second-fix fixtures and equipmentFinished work protected; licensed-trade tests scheduled
8Testing, defect rectification, touch-ups, cleaning and handoverDefects retested and documents assembled

Illustrative 12-week programme

This example allows more separation for a broader home scope, but it still assumes required pre-start approvals and coordinated design information. Custom fabrication, variations, failed tests, restricted work hours, inspections or unavailable materials can move any date.

WeeksIllustrative focusTypical dependency
1-2Protection, demolition, disposal and opening-up checksApproved scope and safe isolation
2-3Masonry, partitions, kerbs and base repairsVerified dimensions and service locations
3-5Coordinated electrical, plumbing, drainage, aircon and ceiling first-fixPoint schedule, equipment data and route checks
5-6Wall closure, wet-area preparation, waterproofing and testsConcealed services accepted
6-8Tiling, ceiling completion, floor bases and paint preparationWaterproofing release and finish set-out
8-9Final flooring and main painting stagesWet work sufficiently complete and surfaces ready
9-10Carpentry installation, doors and hardwareFinal dimensions, fabrication and protected access
10-11Second-fix electrical and plumbing, sanitary ware, equipment and sealantFinished surfaces and service points ready
12Commissioning, defects, retesting, cleaning and documented handoverAll trades complete and utilities available for tests

Use these as dependency examples, not booking promises. For BTO-specific pre-start and handover planning, see the BTO renovation timeline. Wet areas need their own gates; use the bathroom renovation timeline to plan waterproofing, testing, tiling and fixture installation.

Documents to keep the sequence controlled

Budget and scope alignment

Build the programme from an itemised scope, not a finish date alone. The Singapore renovation service guide explains the broader delivery scope, while renovation cost planning helps organise work packages. Any figures published on FixMove pricing pages are FixMove internal planning references, not audited market averages; site measurement, specifications, approvals, access and contractor quotations determine the actual amount.

Need a dependency-led renovation scope?

Send the property type, floor plan, intended changes, target move-in constraints and items already selected. FixMove can help structure a site-specific scope and programme; dates are confirmed only after approvals, measurement, procurement and trade availability are checked.

WhatsApp FixMove

Frequently asked questions

What is the correct order for a home renovation?

Confirm scope and approvals first, then protect and demolish, build and route concealed services, close walls and ceilings, waterproof and tile wet areas, complete flooring and painting in the agreed sequence, install carpentry, fit fixtures, test systems, rectify defects and hand over. The exact order changes with the design and site.

Can a full home renovation always finish in eight weeks?

No. Eight weeks is only an illustrative programme for a controlled, smaller scope after approvals, design decisions and key materials are ready. Hacking, wet works, custom fabrication, inspections, building restrictions, defects, variations and supply lead times can extend the programme.

When should custom carpentry be measured?

Set the design and service requirements early, but take final site dimensions when the surfaces that control the fit are ready or the carpenter has agreed a reliable datum. Releasing fabrication from preliminary dimensions can create gaps, clashes or rework.

Do all HDB renovation works need a permit?

No. HDB states that some renovation works require a permit, while works that do not require one must still comply with its guidelines. Engage a contractor listed in HDB's Directory of Renovation Contractors and do not start permit-controlled work until the required approval is obtained.

Official references

What FixMove does

FixMove (registered ALL-IN-ONE FIX & MOVE, UEN 53505530K) comes to you anywhere in Singapore — your HDB flat, condo, office or shop. There is no counter to visit. One number covers eight kinds of work: aircon, plumbing, electrical, handyman, installation, moving, renovation and full-house customisation. We are open 24 hours, Monday to Sunday, and where the work is regulated we arrange the appropriately licensed person.

Visit charges: A S$10 fuel surcharge applies to every visit. No additional standard call-out or inspection fee applies. Urgent service or a customer-requested appointment time adds one S$30 fee, subject to technician availability and confirmation. The S$30 is a separate service fee. Repair, diagnostic labour and materials are quoted separately; work starts only after customer approval.

WhatsApp +65 9823 7108Call +65 9823 7108