F&B Fit-Out Timeline Singapore: The Honest 12-Week Reality Check

Every F&B founder asks the same question: "How fast can I open?" The honest answer for a standard Singapore restaurant or cafe is 10-14 weeks from signed lease to soft opening. This guide breaks the timeline week-by-week, names the critical-path items, and shows where you can — and absolutely cannot — compress the schedule.

Need a date-locked schedule? Send your lease details and target opening date to FixMove. We'll come back within 1 working day with a Gantt-style fit-out plan, critical-path callouts, and what's realistic vs aspirational.
📱 Request Timeline Plan

The 12-Week Standard F&B Fit-Out (Cafe / Mid-Size Restaurant)

WeekPhaseKey activities
Week 1Brief + Design freezeConcept review, site survey, equipment list confirm, design 3D, mall fit-out manual review
Week 2Drawings + ProcurementConstruction drawings, exhaust hood order (longest lead!), kitchen equipment order, materials specified
Week 3SubmissionsURA (if needed), SCDF, mall fit-out approval, NEA, BCA renovation permit (HDB shophouse)
Week 4Demolition + M&E startStrip, hack, waterproofing tests, electrical first-fix, plumbing first-fix, exhaust ducting routing
Week 5M&E buildDB box install, water + drainage second-fix, AC ducting, grease trap install, gas line (if needed)
Week 6Wet works finishTile work in kitchen, wet area waterproofing layers, ceiling install start, AC equipment install
Week 7Carpentry + CounterBar counter / cashier counter delivery + install, dining millwork, shelving, partitions
Week 8Equipment installExhaust hood install, kitchen equipment install + connection, espresso machine + grinder, refrigeration
Week 9Finishing + LightingPainting, signage, lighting install, AV cabling, POS install, branding stickers
Week 10Testing + CommissioningEquipment commissioning, exhaust + make-up air balancing, plumbing leak tests, electrical safety test, gas pressure test
Week 11SFA + SCDF inspectionSFA pre-inspection, SCDF inspection, defect rectification, mall handover walkthrough
Week 12Soft openingStaff training week, soft launch with friends/family, full menu testing, ramp to public

The 5 Critical-Path Items That Set Your Floor

These items cannot be compressed below their lead times. Plan everything else around them.

1. Kitchen Exhaust Hood (5-7 weeks lead)

Custom-sized stainless hood + ducting + fresh-air make-up unit. Order at week 1. Anything later and you're stretching the schedule.

2. SP Group Power Upgrade (4-8 weeks)

If current supply is <60kVA and you need 80-100kVA (typical for full restaurant), SP application + meter upgrade adds 4-8 weeks. Check power before signing lease.

3. URA Change of Use (3-5 weeks)

Only if your lease isn't already F&B-approved use. If yes, this is a hard 3-5 week parallel-track task. Don't start construction until URA approval is in hand.

4. SCDF Fire Safety Approval (3-6 weeks)

Required for any partition / escape route / assembly capacity. Submit at week 3 to clear by week 8-9.

5. SFA Licence Inspection (2-4 weeks)

Inspection happens after fit-out is "inspection-ready" (week 10-11). Licence usually issued 2-4 weeks later. You can open commercially the day SFA licence is issued, not before.

Where You Can Compress Schedule

Parallel-track design + permits (saves 2-3 weeks)

Most contractors do sequential: design → submit → start construction. FixMove parallel-tracks: design + drawings + permit submission + procurement run concurrently in weeks 1-3.

Pre-aligned SFA layout (saves 1-2 weeks)

Drawings already match SFA zoning standards (raw / prep / cook / plate / wash separation). Saves redrawings after pre-inspection feedback.

Reuse existing F&B infrastructure (saves 3-5 weeks)

Take over a previous F&B unit with compliant exhaust + grease trap = skip 3-5 weeks of new install + permit lead time.

In-stock equipment (saves 2-4 weeks)

Many premium espresso machines and ovens have 4-8 week import lead. Buying in-stock locally is more expensive (+5-15%) but worth it for tight timelines.

Where You Absolutely Cannot Compress

Faster Timelines by Concept

ConceptRealistic MinimumComfortable
Mall kiosk / takeaway4-5 weeks6-8 weeks
Specialty espresso bar5-7 weeks8-10 weeks
Brunch cafe (full kitchen)9-11 weeks12-14 weeks
Sit-down restaurant11-13 weeks14-16 weeks
Multi-bay cloud kitchen12-14 weeks16-20 weeks
Premium fine dining14-16 weeks18-22 weeks

The "Soft Launch vs Hard Open" Distinction

Singapore F&B doesn't hard-open on day 1. Soft opening (friends + family + neighbours) typically runs 1-2 weeks before public launch. This buffer is essential for:

If your "opening date" target is a hard restaurant launch with 80+ covers — add 2 weeks of soft launch buffer to your timeline.

FixMove F&B fit-out specialty: 6-week minimum builds for kiosks; 10-week standard for cafes; 14-week for full restaurants. 100% first-pass SFA approval rate.
📱 Get Week-by-Week Plan

Related Reading

FAQ

How long does F&B fit-out take in Singapore?

Compact F&B: 6-8 weeks. Standard cafe / small restaurant: 10-12 weeks. Mid-size restaurant with full kitchen: 12-14 weeks. Cloud kitchen: 12-16 weeks. Premium fine dining: 14-18 weeks.

What's the longest-lead item in F&B fit-out?

Kitchen exhaust hood + ducting + make-up air unit — typically 5-7 weeks lead time. Always order at week 1-2.

Can I open the F&B in 6 weeks?

Only for compact concepts (kiosk, specialty cafe, takeaway) and only if: lease signed with existing F&B infrastructure, exhaust + grease trap compliant, equipment in stock, SFA pre-aligned.

What causes most F&B fit-out delays?

Top 5: late kitchen exhaust order, URA Change of Use needed mid-project, SP power upgrade lead time, SFA inspection rework, landlord/mall fit-out manual rework.

Published: 10 May 2026 · Updated: 10 May 2026 · By FixMove F&B Fit-Out Team — average 11.2-week delivery across 50+ Singapore F&B projects.